ankuragarwal1982 wrote:I have received the demand of 5% amount on completion of plaster for my flat T8-303.
Isn't it too soon? Has anybody got the chance to check the status of construction personally? Have you also got such a demand letter?
I am wondering if plaster is also done then wht else is left now..just interiors? If they go by this speed then we should get possession by Apr-Jun 2010.
Hi Ankur,
thanks for the update. I would like to update you that I had a word with RPS management on this today morning itself as I wanted to understand the mechanism for further 2-3 demands. I didn't know that you have posted such update in the forum. The demand for completion of plaster would be raised on the basis of completion of each concerned unit/floor wise as opposed to earlier demands which were based on completion of particular stage in the entire tower structure. e.g. in the Tower - 7 (i hold an apartment at 14th floor in this tower).
As of December last week (December 27, being the last uploaded date for photos on RPS Savana website reflecting the status of probably Dec 22 or 23) Tower 7 is at following stage...
Structure complete - Last floor (17) roof slab casting done.
Brick Work - complete till 7th & 8th floor (in progres), so plastering would have started from bottom to these floors by now. As the brick work progresses upwards, plastering will progress similarly and as and when a particular floor gets completed for plastering, demand would be raised for the particular apartments on those floors in respect of completion of plaster.
As of the same date, T-8 is complete in respect of structure, brickwork and grills (like in balconies, bedrooms), window frames.
So plastering, flooring is practically left in it alongwith external and internal whitewash, sanitary fittings etc. Ideally by the last update date of Dec 22 or 23, plastering would have definitely been in progress and might have been completed.
Like in my case, I have evaluated and identified myself some timelines for completion of respective stages of demand like....
Completion of last floor roof slab casting - my idea was that it would either come in latest by 3rd week of Dec or max by last week of Dec, 2009. It actually came in Second Week itself.
Completion of Internal Plaster - I have estimated it to come earliest by Mid of Feb. 2010 or max by March Ist week.
Completion of flooring - expect this demand to come by May 2010 or to the most in June.
My consideration is if all the above stages are actually achieved alongwith whitewash and other things, plus completion certificate from authorities for all towers as well as project, then Time of Possession demand should fall somewhere Sept - Oct 2010 and that is what RPS is trying to achieve as well. Even if all things go well, possession normally takes time bcoz we are talking about handing over of over 2000 apartments and that too across various towers (27 to be precise). So it is my feeling that possession even if done fast would ideally take 2-3 months time to finish off in entirety.
I hope you would get an idea of what I feel.
Best regards,
Gaurav