by ghoshdebasis3 » Mon Aug 27, 2012 11:00 am
Hi,
I have visited RPS Savana site on 26.08.2012.
Some progress is definitely visible in the superstructures of few towers, mainly from T3 to T8 in the form of external plaster, painting and little visible internal development. There is no sign of any type of development in the internal common area except boundary wall. There are no activities towards even towards internal road work. It is quite impossible to make internal common area livable before at least 5-6 months.
However, site office is still saying that the possession will be as per schedule, which is Dec-2012, but they are not having any convincing explanation. Though they were honest enough to declare that T1 and T2 tower which was scheduled to be included in first phase has been excluded now, making these towers first victim of current wave on expectation of possession by year end.
One more hidden cost in the form of ECC and FFC (External Cable Connection and Fire Fighting Cost) is come out during discussion with them. They did not inform the approximate figure but looks to be a hectic amount. I feel this is required to be clarified very soon.
Altogether the situation is grim and some action is required to be taken by our end immediately. Otherwise, we shall have to wait for years after year with the New Year gift every year……… “Possession will be given by the year end”.
Regards
Debasis Ghosh