by yadav_ajay » Wed Jul 04, 2012 12:26 pm
Friends,
I had a meeting with Division -3 XEN and SE-HUDA on 29th June'12.
Here is the outcome.
Q 1.Work Progress on Master RoadA : Master Road work is going in full speed and would be completed in due course of time (by end of next year) for 31KM.
Q 2. Status of Possession of remaining land (21KM).
A : Still pending as there is no agreement is being made between Govt. and Farmers. Farmers are not agree to sign NOC as per conditions of Govt.
Q 3: Why there is halt on Master Sewerage work, there is no Progress since Apr'12. (Since inauguration done be CM on 22nd April’12)
A : There is detail inspection pending of Sewerage Pipes and Contractor is taking time to submit the Pipes to HUDA office and that why it got delayed.
To be started by 10th July’12 (tentative)
Q 4 : DNIT and Tendering Progress on Master Supply
A: Budget of 290cr has been prepared and principally approved by CM in April’12. But HUDA-FBD office still not received the signed copy of approval.
HUDA FBD is taking this with CA HUDA-CHD and hopes it will be cleared with in July’12 and then tendering will start.
( I seen the details DNIT report and it was ready)
Q 5 : Strom Water Provision and Electricity
A : Budget approved and soon tendering will be started. DNIT under preparation.
Q 6 : Status on the connectivity of New Sectors with rest of FBD.
A : HUDA-FBD already received the demand of Rs 50/- Lacs from UP irrigation Dept. for the clearance of 03 Bridges over Agra canal. as per HUDA officials, there were some mistakes in those proposal from UP irrigation dept and would be corrected.
Proposed Bridges Locations are : 1. Sec 87 Outer periphery, 2. Sec 86-87 dividing, 3. Sec 81-86 dividing.
( I have seen that proposal Document and verified)
Regarding the High tension Transmission line, HUDA already asked DHBVN to shift those line, But you all know…how things move in Govt. office.
At the end, HUDA officials told me that, all development work is pending at CHD office and we are sending approval/proposal, but it is not cleared on time from CHD office.
To my surprise, he said that It will take minimum 05 year to get all facilities across new sectors by the current progress/speed.
I told him that already more than 700 families already shifted there and living, he was shocked how can those peoples live there, when there is no basic infrastructure available??
At last, he assured me that HUDA-FBD office is trying their best to carry out speedy development, but somewhere their hands are also tied up.
Hope this will help you guys.
--------------------------------------------------------------------------------------------------------------------------------------------
Regarding the Protest, we are working on the same and at the last stage of fixing the details.within this wk you all members will get update on that.
-------------------------------------------------------------------------------------------------------------------------------------------