by shilpi21 » Tue Jan 03, 2012 3:56 pm
I also have a flat in THE RESORT -BPTP
I too recd. the demand letter.I asked them to send the HUDA memo which they have sent to me.They have also informed that the last date has been extended to 10th Feb 2012.
I have confronted them with my calculations of EDC which is as follows:
a. The entire area of BPTP Resort is 10.92 acre.
b. Now, as per their letter, we found that present EDC charge is Rs. 1,74,94,000 per acre.Hence total EDC charge applicable for entire area of Resort = 1,74,94,000 x10.92,i.e, Rs. 19,10,34,480/-.
That means BPTP has to pay 19 Crores,10 Lakh,34 thousand,4 hundred and 80 to Haryana Govt. for the project RESORT as EDC.
Now total saleable area of RESORT(summing up area of all the units of six towers) is
7,73,500 square ft.
So if we divide total EDC by saleable area we get EDC per sqft buyers have to pay.
It comes out to be 19,10,34,480 / 7,73,500 = 246.97 per sqft ( NOT 310 per sqft AS THEY CLAIM)
This calculation has been done taking BPTP data only (BPTP website+DEMAND letter)
I ASKED THEM "Please tell me how you came to the figure of Rs 310/-. per sqft."
I SENT THIS MAIL TODAY,LET'S WAIT FOR THE RESPONSE