Join us on Facebook
Become a GFWA member

Site Announcements

Invitation to RPS SAVANA Allottees to join Case in NCDRC against RPS Infrastructures Ltd


Have you submitted a rating and reviewed your project?
Rate & Review your project now! Submit your project and review.
Read Reviews! Share your feedback!


** Enhanced EDC Stayed by High Court **

Forum email notifications...Please read !
Carpool from Greater Faridabad to Noida
Carpool from Greater Faridabad to GGN


Advertise with us

All updates regarding SAVANA

Re: Savana visit 22 Nov 12, with Room Photos

Postby sanjeev2111 » Wed Nov 28, 2012 11:58 am

Hi S Rajyam,

The Flat I visited was T8 - 105 so not sure if this was with delux specification or not. But my sense is these woooden work will not be there in normal flats.

for me Sink is very small which RPS fitted in Kitchen.
User avatar
sanjeev2111
GFWA Member
GFWA Member
 
Posts: 84
Joined: Tue Aug 10, 2010 10:06 am

Re: Savana visit 22 Nov 12, with Room Photos

Postby cujatin » Wed Nov 28, 2012 12:19 pm

Hi Sanjeev,

I have one question.

You mentioned the sequence of the possession T8, T7, T4.

in some of the earlier post it was mentioned T8 and T3.

was this sequence given to you officially, I mean which is the more concrete ?
Mine is in T4.

Jatin
User avatar
cujatin
GFWA Member
GFWA Member
 
Posts: 79
Joined: Tue Apr 20, 2010 12:57 pm
Location: Faridabad

Re: Savana visit 22 Nov 12, with Room Photos

Postby ajay2023 » Wed Nov 28, 2012 12:22 pm

Dear Sanjeev,

Thanks for this valuable information. let us assume if possesion will start in coming 4-5 months for completed towers, at this pace RPS will be able to give the possesion only by end of 2014 for all towers as I have in Purple Hazel 3+1 where plaster of outer wall is still pending rest you can assume.

R they allowed site visit?

But any how some light is showing at other end of tunnel.

Best of luck!! :clap: :thumb:

Rgds
User avatar
ajay2023
GFWA Member
GFWA Member
 
Posts: 79
Joined: Fri Feb 05, 2010 12:35 pm
Location: delhi

Re: Savana visit 22 Nov 12, with Room Photos

Postby srajyam » Wed Nov 28, 2012 12:28 pm

Thanks for the infor sanjeev ji.

Regards,

S Rajyam
User avatar
srajyam
Junior Member
Junior Member
 
Posts: 21
Joined: Tue Jun 08, 2010 10:49 pm
Location: Faridabad

Re: Any update on RPS Savana progress?

Postby Azfar » Wed Dec 05, 2012 5:03 pm

Dear All,
Have called up RPS office today and as expected have been informed of further postponment of possession. December 2012 was the month when possession would be offered, as per the builder. But what will be offered in December is just another schedule of possession...
Be prepared for another round of fake dates and endless stories to keep our dreams going, from 2012 to 2013 and so on...
Best wishes,
Azfar
User avatar
Azfar
Junior Member
Junior Member
 
Posts: 23
Joined: Sat Apr 04, 2009 1:23 pm

Re: Any update on RPS Savana progress?

Postby ddamitav » Wed Dec 05, 2012 7:08 pm

yes it is an end less story..... 2 month ago they were up beat and told us we will definitely give possession of atleast 2 towers by Dec 12.

when I enquired how are you going to give possession with the current stage of construction she said that is our look out you need not worry. shame less people.
User avatar
ddamitav
GFWA Member
GFWA Member
 
Posts: 329
Joined: Thu Jul 30, 2009 12:10 am
Location: Mumbai
Location: Mumbai

Re: Any update on RPS Savana progress?

Postby mikesab » Wed Dec 05, 2012 7:16 pm

It is wise to follow your experience in dealing with builders. Look at those towers, there is no way that they would be ready in another 3 months. :) :)
User avatar
mikesab
Senior Member
Senior Member
 
Posts: 104
Joined: Wed Mar 14, 2012 10:50 am

Re: Any update on RPS Savana progress?

Postby yogesh » Wed Dec 05, 2012 7:25 pm

forget the possession in 2012
rps can give possession in mid 2013 for 3-4 towers
they will offer possession in last 2013 for 7-8 towers
and rest will be ready to move in 2014
User avatar
yogesh
GFWA Member
GFWA Member
 
Posts: 218
Joined: Wed Apr 20, 2011 5:02 pm

Re: Any update on RPS Savana progress?

Postby ddamitav » Fri Dec 21, 2012 4:18 pm

Rps has not yet renewed its license which was expired in 2008. since last 3 months
they are saying that concern department is doing the needful and they will start possession from Dec 2012. what a joke !!! guys plz call rps day and night and build a pressure on them
User avatar
ddamitav
GFWA Member
GFWA Member
 
Posts: 329
Joined: Thu Jul 30, 2009 12:10 am
Location: Mumbai
Location: Mumbai

Re: Any update on RPS Savana progress?

Postby s1joshi » Fri Dec 21, 2012 6:10 pm

Has there been any lucky one to receive much proclaimed possession letter or atleast fitout letter from RPS, Or the date for start of phase wise possession hand out has officially been marked for Dec 2013, as has been the story for past several years ?
User avatar
s1joshi
GFWA Member
GFWA Member
 
Posts: 629
Joined: Sat May 16, 2009 2:43 pm
Location: Delhi

Re: Any update on RPS Savana progress?

Postby ddamitav » Fri Dec 21, 2012 6:39 pm

what is the last demand raised by rps. for tower t7 last demand was raised more than 2 years back on account of completion of internal plaster
User avatar
ddamitav
GFWA Member
GFWA Member
 
Posts: 329
Joined: Thu Jul 30, 2009 12:10 am
Location: Mumbai
Location: Mumbai

Re: Any update on RPS Savana progress?

Postby tanejan » Sat Dec 22, 2012 12:25 am

I don't think they are going to give the possession letters this year. Their main focus is on T8 which is almost completed.

I saw the following developments during my visit

1. In T8 external paint was complete (one coat). This is not the final paint.
2. They was working on the Entrance of the Tower T8 (please see the picture of Tower 8 on RPS site)
3. Lifts were getting installed in T8. Its good that the lifts are of KONE.
4. Except Ground floor every other floor was locked (I guess they have completed maximum work in all other floors of T8)
5. Construction of Internal Shops and Temple(between shops and T7) was in full swing.
6. I was told that we will be receiving the Schedule about the possession very soon (its confirmed no possession before Feb / March).
7. Road from the Main Entrance to the towers was being constructed. Main Entrance was looking nice.
8. Street Light were looking nice from the Main Gate to the towers.

RPS has revised the price list again. There is some price hike (in resale)also for the towers which will be getting possession before mid of next year.

These updates are till 9th Dec.

Regards
User avatar
tanejan
Junior Member
Junior Member
 
Posts: 2
Joined: Mon Nov 26, 2012 10:55 pm

Re: Any update on RPS Savana progress?

Postby cujatin » Sat Dec 22, 2012 8:47 am

Dear tanejan,

what was the status for the green area in between towers.

There was some Digging there when I visited last time some Have they made or developing park there ?

Jatin
User avatar
cujatin
GFWA Member
GFWA Member
 
Posts: 79
Joined: Tue Apr 20, 2010 12:57 pm
Location: Faridabad

Re: Any update on RPS Savana progress?

Postby tanejan » Sat Dec 22, 2012 11:26 am

There was some construction below the ground level. I guess that is for Kids play area.

After this construction is over, thn they will be developing green area (park) above it.
User avatar
tanejan
Junior Member
Junior Member
 
Posts: 2
Joined: Mon Nov 26, 2012 10:55 pm

Re: Any update on RPS Savana progress?

Postby nitgood07 » Sat Dec 22, 2012 5:54 pm

Are they allowing site visit from inside of apartments now.. I have apartment in T4 but not sure when they will offer possession. my last visit was before Diwali.. that time they did not allow visit from inside.
User avatar
nitgood07
GFWA Member
GFWA Member
 
Posts: 41
Joined: Tue Jun 28, 2011 9:17 pm