Invitation to RPS SAVANA Allottees to join Case in NCDRC against RPS Infrastructures Ltd Have you submitted a rating and reviewed your project? Rate & Review your project now! Submit your project and review. Read Reviews! Share your feedback! ** Enhanced EDC Stayed by High Court ** Forum email notifications...Please read ! Carpool from Greater Faridabad to Noida Carpool from Greater Faridabad to GGN |
Your new posts and topics will be moderated and will be visible only after approval. Any irrelevant or off-topic post will be deleted. You will not be able see attachments and files in the forum till you have successfully created 5 post in the forum.
vineet wrote:Hi Anuj,
I feel its still a long wait.
Partial OC can not be obtained till 25% of the project is ready with proportionate share of amenities - fire fighting, drainage etc. etc.
Unfortunately our laws, acts and rules give a lot of loopholes for the cheats to play around - the info on website saying they "have applied for OC" is another such example.
- You can apply for OC even when you have not done any construction. There is no rule preventing you from doing so. What matters is whether you get OC.
- 25% of the project would mean at least 5-6 towers. No way these are ready so RPS is just buying time by the statement 'have applied for OC'.
-RPS has not deposited EDC (last RTI reply I have on this is in Feb'13)so logically OC can not be granted to them.