by sanjeev2111 » Mon Jan 10, 2011 4:42 pm
Hi All,
Yesterday I went to see the RPS Savana site and found slow progress and not very enthu about getting possession of all flats by end of Dec 2011. Talked to them and got these inputs:
1. Possession for T8 will be done around Nov -Dec 2010. From the site it looks only T8 is going to be completed by this time and work is going on other towers.
2. Seen the new broucher for RPS savana which they are giving to new customers and in that the max green area is sold out (they said this is as per Haryana society act for providing services to residents).
3. Internal roads work will be taken up before possession.
4. Common Facilities like club will be shared with RPS palms - when I objected.. they said talk to RPS office in Okhla.
5. Few parking lots is sold to nursery schools, dispensary etc. and Front entry green area- for which most of us has bought flat in RPS savana is sold to school and dispensary. When argued about 85 % greenery they said its still there but I failed to understand how they are calculating this and they have no answer but they were adamant on this.
6. 3 +1 BHK flats are in half and will take more than 1.5 yrs to complete on my assumption.
7. On electricity part - they said they have got sanctioned for 66 KVA line and when I asked about letter they referred me to Okhla office.
8. Water - they said they have 6 Borewells digged and 24 hrs water will be there for us.
9. They did not allow me to visit inside the apt and taken only near to tower 8.
10. On carpet area calculations they said that around 15 % area will be reduced for lift, stairs and other common lobby etc.
11. On incident of RPS omaxe green valley where ceiling has fallen off - they said that was 4 ys old and first construction from RPS and this will not be the case with Savana.
happy to discuss more on upcoming meetings or forum.
Sanjeev Kumar
T 8 - 805
92667 30857