by rkj.arti » Tue Jul 01, 2014 9:03 pm
We have paid CAM Bill for the year 2012-2013 and also for the year 2013-2014 (which is more than double, the previous year amount) and the fact that we have given the physical possession in March 2014. Even BPTP without having being prepared for Registration of the plots, have forced us to pay the amount and Sign the BPMS Agreement to get the REGISTRY done.
We have further visited our plot at parksland faridabad site several times. And observed that nothing is being done in the name of upkeeping/maintaining the BPTP Parksland Faridabad.
We have visited the site on Dec 20, 2013 also, when we called up the staff deputed at site, and met Mr. Sanjay also at site office.
During our visit, We found out the following :
There was no display board at the entrance or inside the locality, and
there are no guide maps to reach the desired location.
There was not even a single guard available/seen in the entire location.
Lots of garbage/ polythene waste papers everywhere.
No landscape/parks to maintain.
Multistorey Appts. Builder behind our plot used our plot to
Ply heavy vehicles loaded with building raw materials resulting
In land soil sinking further down, pavers broken down to pieces.
Roads are in bad shape/ No sweeping of roads at all.
The street lights were not functional at all.
There is no boundary walls or fencing.
No activity of clearing unwanted growth of plants in vacant plots
More looks like location of grazing cattle.
[size=150]Please find attached photographs in support of the above raised
points.
That's why when you raised CAM bill for the year 2014-2015
We requested BPMS to please send us the last two year expenditure account/Profit & Loss a/c along with the audited balance sheet so as to identify, the reason for such high costs charged by BPMS for vacant plots having zero percent construction activity in such a newly developed big project, delay on account of this will result in non submission of this amount, being a member of the BPTP society we have every right to ascertain the causes for such escalated high maintenance cost even after REGISTRY falling which we shall move in competent court of law against you at your cost, risk & consequences, please note.
It's not that we have signed the one sided BPMS agreement, drafted in favour
of the builder for the builder and one of the binding to get the registry done, gives free hand on a/c of CAM, (having taken maintenance money without any work in the past two years 2012-2014)
Maintenance Charges shall mean charges as may be demanded by the Maintenance Service Provider towards the regular upkeep, security and maintenance of the Colony which includes maintenance, security, landscaping and common areas and facilities with respect to their regular upkeep, maintenance. ( NOT OTHERWISE )
So, we request BPMS to withdraw CAM bill raised for the year 2014-2015, which is illegal and unlawful