Join us on Facebook
Become a GFWA member

Site Announcements

Invitation to RPS SAVANA Allottees to join Case in NCDRC against RPS Infrastructures Ltd


Have you submitted a rating and reviewed your project?
Rate & Review your project now! Submit your project and review.
Read Reviews! Share your feedback!


** Enhanced EDC Stayed by High Court **

Forum email notifications...Please read !
Carpool from Greater Faridabad to Noida
Carpool from Greater Faridabad to GGN


Advertise with us

Connect with residents of ERA Divine Court, Sector 76 Faridabad

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby laxmiashverya » Fri Nov 28, 2014 1:03 pm

I have also taken loan from HDFC and paying EMI for the past 2 years. I would also like to be included in action against HDFC if we are taking any as a group.
User avatar
laxmiashverya
Junior Member
Junior Member
 
Posts: 7
Joined: Tue Dec 10, 2013 5:20 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Fri Nov 28, 2014 1:16 pm

Pls contact Mr Aashish Kaul ji 9958686328, as he had filed a Complaint to RBI against the banks financing era divine court in the month of January february 2014. He would also guide in this action.
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby ssp142000 » Fri Nov 28, 2014 1:38 pm

HDFC is a Foreign Owned Private Bank (equity held by foreigners). Here only to exploit and make unruly profit and gains.

Managers are assigned targets and rewards. Compelling them to exploit rules and regulations.

Not a single nationalised bank will do what this bank has done.

Its time to get together and act against these banks'.

We need to come up with an appropriate plan of action to bring them to books.
Thanks

Shamsher
User avatar
ssp142000
GFWA Member
GFWA Member
 
Posts: 107
Joined: Thu Mar 10, 2011 9:19 am
Location: Faridabad

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Fri Nov 28, 2014 2:24 pm

Corporation bank also gave home loan on Era divine court.
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Fri Nov 28, 2014 2:34 pm

You do not have the required permission to view the files attached to this post. Read FAQs
Or you must LOGIN or REGISTER to view these files.
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Fri Nov 28, 2014 7:19 pm

naveenarichwal wrote:Courtesy Mr Binod Kumar-9968090148

Dear friends,


due to our continuou hard work to legalise this project, we have been able to get a major boost in our efforts. We filed a writ petition in Chandigarh Hight court and court understood our agony and instructed DGTCP Chandigarh to take remedial measures to hand over the project to us. It is great victory for us. For this I like to thank especially Ankur, Harjit, Vibhuti, Mohit, Dipak, Amit, Pankaj, Abahy, Mahesh and Govind who took initiatives to file this writ petition. Also thank to Vishal who filed separately. The order can be downloaded from..http://phhc.gov.in:8080/pdf/fo/CWP_2348 ... _ORDER.pdf


Binod

BINOD JI AND HIS GROUP MEMBERS HAVE DONE A COMENDABLE ACT WHICH WILL BE BENEFICIAL TO ALL IN FUTURE . HIS GROUP PLANS TO CARRY OUT FUTHER ACTIONS THAT WILL LEAD TO THE LEGALIZATION OF THE PROJECT AND ALSO EARLY POSSESSION. WE SHOULD SUPPORT THE GROUP WHICH HAS ALMOST 80 BUYERS AND MORE NUMBER OF BUYERS SHOULD JOIN HIM IN THEIR EFFORT.

HE HAS FORMED A WHATSAP GROUP AND EVERYBODY SHOULD JOIN TO STRENGTHEN THE GROUP IN THEIR EFFORT FOR EARLY LEGAL POSSESSION.

HIS MOBILE NO. IS 9968090148
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Fri Nov 28, 2014 11:59 pm

If HDFC Ltd. is a Bank than read this alsoas an easy option
http://www.jagoinvestor.com/2011/04/ban ... dsman.html
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby umesh.prabhakar1965@rediffmail.com » Sat Nov 29, 2014 8:09 am

Thanks Naveen ji for sharing the information. The Banking Ombudsman is working on complaints with regard to banking only.

The housing loan is regulated by NHBFC.
User avatar
umesh.prabhakar1965@rediffmail.com
GFWA Member
GFWA Member
 
Posts: 267
Joined: Sun May 22, 2011 7:25 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Sat Nov 29, 2014 9:15 am

http://rbi.org.in/scripts/FAQView.aspx?Id=71

26. Is there an Ombudsman for hearing complaints against NBFCs?

No, there is no Ombudsman for hearing complaints against NBFCs. However, in respect of credit card operations of an NBFC, if a complainant does not get satisfactory response from the NBFC within a maximum period of thirty (30) days from the date of lodging the complaint, the customer will have the option to approach the Office of the concerned Banking Ombudsman for redressal of his grievance/s.

All NBFCs have in place a Grievance Redressal Officer, whose name and contact details have to be mandatorily displayed in the premises of the NBFCs. The grievance can be taken up with the Grievance Redressal Officer. In case the complainant is not satisfied with the settlement of the complaint by the Grievance Redressal Officer of the NBFC, he/she may approach the nearest office of the Reserve Bank of India with the complaint. The details of the Office of the Reserve Bank has also to be mandatorily displayed in the premises of the NBFC.
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Sat Nov 29, 2014 12:45 pm

Financial companies and their regulators.
You do not have the required permission to view the files attached to this post. Read FAQs
Or you must LOGIN or REGISTER to view these files.
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Sat Nov 29, 2014 1:30 pm

http://hrlokayukta.gov.in/
The establishment of the institutions of Lokayukta is part of an ongoing effort to provide clean, transparent and accountable government to the people. Lokayukta today are the institutional manifestations of the need to provide a quasi-judicial body, which would act as a watchdog to pinpoint wrong doings of the administration, look into complaints of the victims of corrupt elements and suggest measures to improve the effectiveness and efficiency of our Government.

Lokayuktas have been unearthing corruption cases, recommending measures to redress grievances of the people and above all, acting as a much needed safety valve to release the bottled up pressure of aggrieved citizens, which, if allowed to accumulate, would put a question mark on the credibility of our administrative apparatus. The very existence of a Lokayukta helps to generate a feeling of assurance among the public at large, that they have a mechanism to fall back upon when faced with corrupt public servants.
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm


Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby ssp142000 » Mon Dec 01, 2014 11:57 am

Lets file a Writ Petition asking to Direct CBI investigate into the matter of ERA, Countrywide, DGTCP and Banks.

Lets see how the corrupt (many intelligent IASs') have hedged themselves from prosecution.

This writ petition, by way of public interest litigation, is filed seeking a direction to the respondent No.1- Central Bureau of Investigation (CBI) to register a criminal case against the respondents 3 to 5 under the provisions of Indian Penal Code, 1860 read with Prevention of Corruption Act, 1988 and investigate into the colony licenses issued by the Department of Town and Country Planning (DTCP), Haryana during 2005 to 2012 allegedly in contravention of the provisions of the Haryana Development and Regulations of Urban Areas Act, 1975 as well as the alleged illegal land deals in the State of Rajasthan creating huge loss to the public exchequer.
Thanks

Shamsher
User avatar
ssp142000
GFWA Member
GFWA Member
 
Posts: 107
Joined: Thu Mar 10, 2011 9:19 am
Location: Faridabad

Re: ERA Divine Court construction status and updates, possession, resale prices discussion

Postby naveenarichwal » Mon Dec 01, 2014 5:59 pm

The Court has given Specific Direction to DGTCP and also given a Time frame to take action as per Law , so the Time frame of 3 months is a time of moratorium for victims, because nobody will listen to anything before 3 months.

3 months is the time for drawing out the best action Plan to face the worst. The petitioners and the lawyers who have strategised the CWP are the best persons as to decide on this further course of action, The Buyers should support the Group of Binod Kumar Ji in Increasing Numbers and form a formidable group.

This 3 month time is their to Join hands together.
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm