Follow @Myfaridabad |
Site Announcements |
---|
Invitation to RPS SAVANA Allottees to join Case in NCDRC against RPS Infrastructures Ltd Have you submitted a rating and reviewed your project? Rate & Review your project now! Submit your project and review. Read Reviews! Share your feedback! ** Enhanced EDC Stayed by High Court ** Forum email notifications...Please read ! Carpool from Greater Faridabad to Noida Carpool from Greater Faridabad to GGN |
satpalsharma wrote:I'm also hopeful by end of dec 2010 only. However will the penalty clause kick in once they pass that time also.. I mean if they go beyond 2010? Any thoughts?
Jayanta wrote:satpalsharma wrote:I'm also hopeful by end of dec 2010 only. However will the penalty clause kick in once they pass that time also.. I mean if they go beyond 2010? Any thoughts?
When did you book the apartment? I had booked the apartment in Sep 2006 and they had a 3 year possession or penalty clause. So when I enquired about the penalty clause because it became applicable from Sep 2009, they had a different answer.
mkpawar wrote:Jayanta wrote:satpalsharma wrote:I'm also hopeful by end of dec 2010 only. However will the penalty clause kick in once they pass that time also.. I mean if they go beyond 2010? Any thoughts?
When did you book the apartment? I had booked the apartment in Sep 2006 and they had a 3 year possession or penalty clause. So when I enquired about the penalty clause because it became applicable from Sep 2009, they had a different answer.
True - Mine also was booked in Sep'06 with Buyer -agreement executed in Somewhat Oct'06. BTW what answer you got from them. In fact - we already know the major cause for whatever dealy is delay Map approval which RPS could not be blamed for. Positive part till now- RPS is trying it's best.
Dear Madam,
Warm Greetings from RPS Group. We acknowledge your association in Group Housing Project ‘SAVANA’. We would like to update you that construction work at site ‘SAVANA’ is in full swing. Latest updates about site progress are available on our web site www.rpsgroupindia.com & www.rps-savana.com.
We are in receipt of your mail dated xx/xx/2009 in which you have mentioned about the penalty on account of delayed possession. In this regard we would like to intimate that as per agreed terms, the possession of unit will be offered within 36 months from the date of execution of buyer’s agreement subject to time taken by govt. authorities in according various sanctions/ approvals and subject to circumstances beyond the control of developer (duly mentioned in buyer’s agreement / Booking form). Both the parties are bound by agreed terms of contract and the same will be complied with.
It is our earnest endeavour to offer the possession of units in project ‘SAVANA’ by the end of year 2010. Kindly extend your co-operation for successful execution of project ‘SAVANA’.
Please feel free to contact us at 011-40543200 for further details.
Thanks
Rajesh Jain
RPS Group
Users browsing this forum: No registered users and 4 guests