Invitation to RPS SAVANA Allottees to join Case in NCDRC against RPS Infrastructures Ltd Have you submitted a rating and reviewed your project? Rate & Review your project now! Submit your project and review. Read Reviews! Share your feedback! ** Enhanced EDC Stayed by High Court ** Forum email notifications...Please read ! Carpool from Greater Faridabad to Noida Carpool from Greater Faridabad to GGN |
Dear Sir/Madam,
Good Day!
On the behalf of Greater Faridabad Welfare Association (GFWA),
I would like to update you about our meeting with DC- Dr Praveen Kumar and Various builder, DTP Faridabad held on 20th May’11 (today) at Conference Hall, Mini Secretariat, Sector 12, Faridabad
Pls find below Minutes of Meeting:
(Media Article)
Meeting was chaired by Dr. Praveen Kumar and attended Mr. Sanjeev Maan (DTP- Faridabad), Mr Davender Pal (DTP Enforcement) and XEN- HUDA from Govt side.
Around 70 members were present from various societies from Greater Faridabad region to put their grievances to Hon’able DC.
As DTP issued meeting call notice to 13 builders, but only 6 builders (BPTP, KLJ, RPS, Shiv Sai, Piyush and Omaxe )came to attend this meeting.
Taking this as dishonoring the orders, DC- Dr Praveen Kumar instructed Mr Sanjeev Maan (DTP) to send notice to all absent builders for ignoring orders.
SRS, PAL, Triveni, Puri, SPR, ERA and Uppal builders are among those who have skipped this meeting and not honored to DTP call.
During discussion various issues were taken up and DC –Dr. Praveen Kumar carefully listened all issues.
Here are some Major Points of discussion:-
- Delay in Possession
- Not honoring delay Penalty
- Sale of common area
- Handing oven Possession without Govt approvals
- Forcefully asking buyers to sign “Undertakings”
- Not giving physical possession to customers despite that customers paid their 100% full and final amount.
(some cases examples attached herewith for your reference)
On the above issues (as these were common issues from all home buyers against all builders) ;
DC –Dr Praveen Kumar Instructed that :-
- All Builders to give possession at the earliest and to follow their commitment to home buyers.
- All builders should Honor penalty clause as per the agreement with bank interest.
- All Builders will Provide the Layout Plan, building Plan, Maps approval and other relevant documents to Customers as per Town and Country Planning Public Notice.
If any builder not following this, then DC office will take action against those builders.
- Interest to be paid by builder to customer on extra charges which builder collected from home buyers.
- Committee to be formed under the chairmanship of ADC (Additional Deputy Commissioner) to enquire and look after the customer complaints of all builders and this committee will check the quality of construction, enquire about the reason of delay of construction and Video graphing to be done during their audit as evidence. Based on Committee report and findings, DC office will take action against the builders.
- Immediate action and notice ordered for SRS and Piyush group as their complaints were more severe as builders are violating law and causing harassment to customers.
- No Customer will sign any undertaking by forcefully from builders and is any such case, same to be reported to DC office. As he said-no one is above law.
- For cheating and misleading to homebuyers for unilateral changing and selling the green/common area(e.g.RPS,Piyush,SRS etc) after selling project by builders, DC ordered to DTP to verify facts with original approved map and submit report. Once found true ,DC will himself initiate FIR against those builders.
DC also instructed XEN-HUDA to prepare: Requirements, details action plan with deadline to complete the development work in the area of the Greater Faridabad and asked him to submit all details within one week time.
DC assured all home buyers that Govt. will not tolerate any violation of Law either by builders or by anybody. If someone found guilty in such cases, strong action will be taken against those.
At last, he said that he himself will monitor these complaints and DTP will submit reports to him on all complaints within a week time.
He also assured that if number of complaints are more, then he will call one by one all builders and will fix up meeting twice in a week to resolve the issues at the earliest.
Also, all builders are given one week time to revert back on the complaints by customers.
GFWA team extended their thanks to him for conducting such a detail meeting and giving his valuable time, cooperation and his commitment for the solution of builder related issues.
Now, GFWA team, feels some hope in district administration and hoping that with the help of district administration these issue will resolve at the earliest and we will get our dream homes very soon.
From GFWA team : Mr Jayanta, Narendera Chhabra, Dheeraj Jain, Ajay Yadav, Manish Gupta, A.K. Gaur , Vineet Mishra, Mrs Vinita Nandwani, and Dharmendra Kumar attended this meeting
In case, of any further information required, pls revert back to me.
Also, We would be giving regular follow up of this meeting.