by anujft » Thu Jul 28, 2011 2:16 pm
Builders, buyers have to go by the agreement
Does the builder have unrestricted powers whenever the agreement clauses are open ended? finds out C.H.Gopinatha Rao
What if when a buyer and builder fault in the agreement in they have entered into? Is the builder vested with unrestricted powers whenever the agreement clauses are open ended and lacks resolution? The Supreme Court case involving DKF Universal Ltd and EktaSeth discusses the above point.
A flat along parking space was booked in 1993 in DLF Residency park, Gurgaon for a sale price of Rs. 16,37,488 payable in 42 instalments spread over a period of ten years commencing from 1993.
The buyer paid a total sum of Rs. 9,94,836 up to September 1998. The builder, on his part, instead of delivering the apartment within three years from the date of booking delayed the completion.
In addition, the builder also demanded an additional amount of Rs. 4,21,474 towards cost escalation, increase in area and external electrification, fire fighting systems and stand by generator.
The buyer declined to pay the revised amount since she found it beyond her paying capacity. She also complained that the delivery of flat was delayed.
However, the builder cancelled the allotment, the earnest money of Rs. 1,69,012 was forfeited and the balance amount returned.
Unfair trade practice
The buyer approached the Monopolies and Restrictive Trade Practices Commission contesting it. The commission recorded that the action of the builder in increasing the cost resulting in the cancellation was an unfair trade practice.
It also observed that the builder had no right to forfeit the earnest money. Consequently, a direction was issued that the builder should return the earnest money with interest thereon at 9% per annum from the date of withholding the earnest money till the date of repayment. Aggrieved by the decision, the builder appealed to the Supreme Court.
The Court observed that the parties to the contract were governed and bound by the terms and conditions of the agreement entered into. The buyer at the time of signing the agreement was well aware of the fact that additional amount would be demanded on account of factors enumerated in the provisions of the agreement.
But what would be the maximum enhancement was not prescribed in the agreement. By inserting the words “the decision of the company in this regard would be final and binding on the allottee”, the company had vested in itself unrestricted power to increase the cost.
The builder also could not give possession within three years from the date of booking and it was also evident that the apartment was incomplete.
As per the agreement the only option given was that if there is delay in delivering the possession, the allottee would be entitled to refund of entire amount deposited with the builder without any interest. This means no liability will accrue upon the builder due to delay in handing over possession.
Considering the facts and circumstances of the case, the court felt that in exercise of their discretionary jurisdiction under Article 142 of the Constitution of India and in the interest of justice directed the builder to return of 50% of forfeited amount while the remaining 50 % stood forfeited.
The Supreme Court made it clear that the direction should not be considered as a precedence in such issues. What this holds for all the buyers is that they must carefully scrutinise the agreement document and take care of all clauses and particularly look at additional costs and other commitments. It also auctions the builders that they cannot assume unrestricted powers in decisions that affect both the parties.
The author is former National President, Institution of Valuers.