by Ajay764_1 » Mon Sep 05, 2011 2:01 pm
Sent the email to Shivsai on 26-Aug-11
Dear All,
I booked subject flat in your Ozone Park project, for which commencement was started in the beginning of the year 2007. Project was suppose to finish in 30 months e.g. in the end of year 2009. I had made the 95% of payment till 25-Aug-2009 and Rest 5% payment is due as per attached payment plan I am still wonder 95% work is completed on time and the project was reviewed by HDFC and payment has been released from the Bank on time but to complete the 5% work it takes 20 months (as on date 26-Aug-2011) and still I have not get the possession letter ,Could you Pls chase up and review once again why the project is on further delay?
Note: I am suppose to get Penalty, as per clause of the agreement I am entitled to get Rs 3.0 psf of the super area e.g. Rs. 1795 psf which comes out Rs. 5385 per month with an interests of 18% as per your agreement followed by 24% after three months. The interest can be calculated using software on monthly basis.
-----------------
Received the reply from A Sen Gupta on 26.08.11
Kindly refer to your mail dated 26.08.2011.
Construction work in the project is going on in hectic pace. Occupancy would be offered by the end of this year.
The delay in construction was due to 'Force Majeure' condition. Force Majeure means unforeseeable events which excuse from fulfiling contract for various reasons which are beyond control. Construction work was hindered owing to such reasons leading to such delay. As per clause 17 of Builder/Buyer Agreement no claim by way of damages/compensation shall lie against the Developers in case of delay in handing over possession in such cases
--------------------
Sent the email to Shivsai on 30-Aug-11
Hi Asen,
It has been verbally agreed in my last meeting that Penalty will be given If any delay of possession. How come this clause 17 comes in picture.
Pls elaborate 'Force Majeure' condition !
-------------------------
Received the reply from A Sen Gupta on 02.09.11
Respected Sir,
Kindly refer to your return mail dated 01.09.2011.
In this connection, your kind attention is invited to my mail dt 30.08.2011 sent in reply to the point that some body has promised to pay penalty for delay in construction as mooted by you. This is contrary to the provision of clause 17 of the Builder/Buyer Agreement.
Sir, I shall be very grateful to have point specific clarificatory reply to my mail dated 30.08.2011 so as to kindly enable me to examine the matter in the proper perspective.
Sir, very humbly I assure you complete satisfaction in regard to the points raised by you in your mail dated 01.09.2011.
-------------
Sent the email to Shivsai on 1-Sep-11
Thanks for the given the reply!
With regard to the specifics you are seeking , it was a verbal assurance give by the people responsible at your construction site office that Penalty will be given If any delay of possession
So, Pls examine the matter as stated in my attached document that when 95% work was completed on time and the corresponding payment towards this has been released from HDFC bank on time in Aug 2009. Now my concern is how come only 5% of the total work comes under clause 17, which effectively resulted in delaying the possession for 20 months as on date.
-----------------------
Received the reply from A Sen Gupta on 02.09.11
Respected Sir,
Kindly refer to your return mail dated 01.09.2011.
You must be well aware that 'Force Majeure' element is an internationally accepted condition of contract / agreement. Your kind attention is invited to our mail reply dated 30.08.2011 wherein it was mentioned specifically that delay was due to Force Majeure condition. We also want you to very kindly note that there is no statutory provision for certifying or authenticating of such condition by any authority.
Sir, you are our valued customer and we share your constraints. We are least inclined to enter into any argument with you. It doesn't augur well with so precious a relation. If you could kindly make it convenient to come to our office with prior telephonic appointment we will place before you documented records for your perusal.
--------------------------
Sent the email to Shivsai on 3-Sep-11
Hi A Sen
As already raised, my concern about asking to refer to clause 17 of ‘Force Majeure’ for nonpayment of penalty against delay in possession of flat:
As correctly mentioned by you Force Majeure means unforeseeable events excluding a person from fulfillment of a contract.
Would like to seek your kind attention to the Force Majeure clause in brief:
Force majeure (French) "superior force", "chance occurrence, unavoidable accident", is a common clause in contracts that essentially frees both parties from liability or obligation when an extraordinary event or circumstance beyond the control of the parties, such as a war, strike, riot, crime, or an event described by the legal term act of God (such as flooding, earthquake, or volcanic eruption), prevents one or both parties from fulfilling their obligations under the contract.
However, force majeure is not intended to excuse negligence or other malfeasance of a party, as where non-performance is caused by the usual and natural consequences of external forces (for example, predicted rain stops an outdoor event), or where the intervening circumstances are specifically contemplated.
I do not find anything happening (flooding, earthquake, or volcanic eruption) after my last payment on Aug 2009, and HDFC had reviewed the project and cleared my payment on Aug 2009 and also I have not received any such notice from M/s Shiv Sai Infrastructure Pvt. Ltd. stating the Force Majeure condition in the construction area since Aug 2009.
If at all Force Majeure clause is valid you need to provide the sufficient documents against the clause ( Why Clause - 17 Applicable only 5% of the total work effecting between Aug 2009 to Sep 2011) Otherwise the point raised for Force Majeure becomes null and void.
In case of not providing satisfactory documents, Shiv Sai Infrastructure Pvt. Ltd. is bound to pay the penalty and expenses occurred (rent paid) due to delay in possession for 20 months so far
In case of nonpayment of penalty towards delay in possession, we will be compelled to take necessary action (moving Court of Law and disclosing the facts with Media) against Shiv Sai Infrastructure Pvt. Ltd.