I visited Ozone square yesterday, here are the points for your reference.
1. Highlight :- Road work is going on. They have laid the black carpet on some 200 mtr road, quality is good, main divider have been built, side drainage is also built on some potions.
Lowlight:- We traveled on the road till Nehar, some potion near to end point has not been aquired. approx 100 mtr. At same ;location HUDA will make connecting bridge also. That is also not seen . Road from the starting point at Nehar till our project is laid into pieces & minimum 4 to 5 small pulias are to be built to connect at all.
2. Approx 100 laborers were working on site, which is good for us. I met Praveen Khurana also on site along with Contractor. They said Huda had asked for 1.5 years to make all raods etc till our door step. Of which 6 months have been passed. Building completion/progress is linked with road progress.
Lowlight:- 24 mtr sector road land is not acquired yet (As per Mr. Khurana).
3. Brick work on all towers is competed. Internal plaster is going on 8th floor at tower-D.
No plaster on external wall except tower A.
New rates for purchase is 3000 sqft.
I can send you pics if u need, send me test mail at
parveen123456@gmail.com. Don't know how to attached here.
regards
Parveen Singh