Join us on Facebook
Become a GFWA member

Site Announcements

Invitation to RPS SAVANA Allottees to join Case in NCDRC against RPS Infrastructures Ltd


Have you submitted a rating and reviewed your project?
Rate & Review your project now! Submit your project and review.
Read Reviews! Share your feedback!


** Enhanced EDC Stayed by High Court **

Forum email notifications...Please read !
Carpool from Greater Faridabad to Noida
Carpool from Greater Faridabad to GGN


Advertise with us

Connect with residents of ERA Redwood Residency, Sector 78 Faridabad.

Re: ERA Redwood Residency - Delay in Construction

Postby psinghal » Sun Mar 22, 2015 11:48 pm

Is there any news on Era Low Rise Floors ?
User avatar
psinghal
Junior Member
Junior Member
 
Posts: 21
Joined: Fri Jan 10, 2014 8:15 pm

Re: ERA Redwood Residency - Delay in Construction

Postby RohitGupta0087 » Wed Mar 25, 2015 11:37 pm

Now Tower D got the OC, how long will it take for possession of Tower A ?
RohitGupta0087
Junior Member
Junior Member
 
Posts: 2
Joined: Tue Sep 09, 2014 11:05 pm

Re: ERA Redwood Residency - Delay in Construction

Postby naveenarichwal » Sat Mar 28, 2015 9:26 am

Looks like 2 years after the work is started and continued uninterrupted with clear intention for delivering.

Presently even D tower is Not Livable ,and i dont know on what basis the DTCP has granted OC to this tower,

Even after getting OC, there are no labour seen in the Tower to complete the remaing work for delivery.

The Intentions of this builder are clear that its main objective is to snatch money in name of delivery of flats,but no intention to deliver them.

Site visit will reveal the truth.
User avatar
naveenarichwal
GFWA Member
GFWA Member
 
Posts: 1102
Joined: Mon May 23, 2011 8:44 pm

Re: ERA Redwood Residency - Delay in Construction

Postby Naveen58 » Mon Apr 13, 2015 9:45 am

Hi All,

I have a 3BHK flat in Tower D of Era Redwood Residency. I have been receiving reminders from the builder since last 2 months for making remaining payment and as per them Flat is ready for possession. But when I visited the site 10 days ago there was no labour available on site and also tower is not complete yet.

They have also changed the Project name to Adel Landmarks with no prior notification of such change.

Please advise should we make arrangement for the payment or wait further ? Moreover, are there any other occupants of Tower D who have received similar payment reminders from the builder?
Naveen58
Junior Member
Junior Member
 
Posts: 1
Joined: Mon Apr 13, 2015 9:06 am

Re: ERA Redwood Residency - Delay in Construction

Postby arppie » Wed Jun 24, 2015 9:26 am

Minutes of Meeting of Redwood Residency RWA (RRFOA) Dated 21.06.2015

1. President welcomed all the members with congratulations for "World Yoga Day".

2. All the points of last meeting were explained and approved by the presented members.

3. Achievements of Redwood Residency RWA (RRFOA) since first meeting were distributed to all presented members and discussed in details.

4. Income and Expenditure, Payment and Receipt accounts and Balance Sheets accounts was discussed in details and approved by the presented members.

5. Consumer court case and modalities were discussed in in-depth details.

6. Mr. M K Khurana as Advisor, Mr. Pankaj Kesri as Co-opted Member and Mr.
Ravinder Goel as Financial Auditor have been taken in the executive committee to strengthen the committee.

7. Few members of executive committee are not attending the monthly meetings due to various personal reasons. Intimation has been sent to those committee members to remain present on next meeting/ activities and future events. In case of their failure to be present the remaining executive committee members will opt new members in their replacement. However they will continue to remain as our honorable members as RWA very well understands individual personal commitments and spare time available varies from one individual to the other.

8. It was proposed that apart from monthly meetings, some social activities in the society will be explored and carried out on regular intervals. Any suggestions for the same are welcome.

9. Problems from individuals were discussed in details and concerns from all individuals were resolved.

10. During the various meetings held with ERA Management , Capri and other authorities association has discussed various points for which some action has been taken by ADEL. Following development has taken place in the society.
a) Three benches for sitting in the EFGH premises were provided.
b) One bench with two rides were provided between Club and Tower D. Jhulas installed in tower I.
c) Street Lights were installed in ABCD premises. Lights in all floors of tower D.
d) Finishing materials were ordered for tower B and C.
e) Receiving of finishing material for Tower C in process.
f) Labor is engaged for finishing of tower C.
g) Labor is engaged for completing of flats in tower DEF.
h) Lift in Tower D becomes operational.
i) There will be increase in labor from July onwards to finish the ABC towers.
j) Finishing work in lot of flats of DEF towers has been initiated by ERA Project In charge.

Credit for the above goes to each one of us who have continuously followed up at various instances and put pressure on ERA to deliver. Kudos of our Unity which should boost our confidence to achieve much more.



11. 9 new members has joined the group from last meeting.

12. Next meeting is decided on 19.07.2015 at 11 am at Redwood Residency.

13. Our priority focus areas will be completion of A,B,C towers and improving livability in the society.

14. All members were advised to give any of their individual issues in writing to Mr. Vivek Gupta/CRM and cc to RWA Email ID at eraredwood78@rediffmail.com for proper documentation and follow up.
15. The meeting was ended with vote of thanks.

thanks & regards,
piyush gupta
B-032
9717786523
You do not have the required permission to view the files attached to this post. Read FAQs
Or you must LOGIN or REGISTER to view these files.
User avatar
arppie
GFWA Member
GFWA Member
 
Posts: 41
Images: 11
Joined: Wed Mar 02, 2011 12:50 pm

Re: ERA Redwood Residency - Delay in Construction

Postby arppie » Mon May 09, 2016 3:18 pm

Hi Members,

Those have flat in ERA Redwood Residency B & C Tower, There is a scheme launch by ERA to complete the your Flat in next 90 days.

There is 5 phase structure plan. Those who are interested Please contact Redwood Residency Flat Owners Association on 15 May 9.30 AM at redwood sector 78 site Near Tower D.

Regards,

Piyush Gupta
B-032
9717786523
User avatar
arppie
GFWA Member
GFWA Member
 
Posts: 41
Images: 11
Joined: Wed Mar 02, 2011 12:50 pm

Re: ERA Redwood Residency - Delay in Construction

Postby arppie » Wed Jun 08, 2016 5:22 pm

Letter to Adel for Possession of flat in B & C Tower.

piyush gupta
9717786523
You do not have the required permission to view the files attached to this post. Read FAQs
Or you must LOGIN or REGISTER to view these files.
User avatar
arppie
GFWA Member
GFWA Member
 
Posts: 41
Images: 11
Joined: Wed Mar 02, 2011 12:50 pm

Previous

Return to ERA Redwood Residency

 


  • Related topics
    Replies
    Views
    Last post

Who is online

Users browsing this forum: No registered users and 0 guests

cron